Sagot :
Answer:
- 10 men
Step-by-step explanation:
Amount of work done by 15 men is:
- 15 men *25 day = 15*25 man*days
Same work can be done by 25 men, in 15 days, so 10 more men should be added.
Answer:
Step-by-step explanation:
Amount of work done by 15 men is:
Same work can be done by 25 men, in 15 days, so 10 more men should be added.