Answer:
Please find the attached file of the complete question:
Explanation:
Please find the attached file of the solution:
Critical Path: ACH
Duration: 21
Because C is on the Critical Path, it cannot be postponed without causing the project to be delayed.
E is not on the critical path, thus it may also be delayed by two weeks without causing the project to be delayed.
[tex]D : ES : 6, EF : 10, LS : 7, LF : 11[/tex]